Over 10 years we help companies reach their financial and branding goals. Engitech is a values-driven technology agency dedicated.

Gallery

Contacts

R&D Center

NeXHS Renewables Private Limited Module 4, Seventh Floor – Block B – Phase II, IIT Madras Research Park, Kanagam Road, Taramani, Chennai – 600113, Tamil Nadu, India.

info@nexhs.com

+91 87544 34872

Retrofitting and Rehabilitation

NeXHS is actively involved in the rehabilitation and retrofitting of wind turbines. NeXHS utilises its technical expertise in the design and construction of wind turbines to identify the cause of damage or deterioration of the structure and how to increase its service life. A detailed evaluation and site investigation is carried out to identify and understand the root cause of the problem. Reports from NDT testing, Concrete Core analysis, Borescopy etc., were evaluated in detail before providing the solution. The structure is also analysed using the Finite Element Method to understand the damage and to propose an effective and optimum solution.

Various problems of the WTG Foundation

Spreading of completely dried concrete without proper compaction

Cracking and Popouts on the surface of the concrete

Delamination of Concrete in the Pedestal Zone

Exposed rebar in pedestal zone

Exposed rebar in pedestal zone

Cold Joint in different portion of raft

Core samples extracted from cold joint areas

Delamination of Concrete in the Pedestal Zone

Process of WTG Foundation

Determining the modulus of elasticity of concrete in compression by means of an extensometer

Core samples of foundations

Visual quality inspection work using a Borescope (After core drilling)

UPV

UPV equipment consists of a Generator that generates an electrical pulse, two transducers (transmitting and receiving transducers), an amplifier, and a time interval measuring device.

The approximate extent of imperfections like voids or low compaction needs to be determined by conducting UPV tests in the WTG locations, as the Elastic stiffness and mechanical strength properties have a direct influence on the velocity of the Ultrasonic pulse.

Pulse velocity is measured by placing the transducers on the same face, in both the WTG Concrete foundations (indirect or surface transmission). As per BS 1881, a minimum path length of 400mm for indirect transmission is recommended.

Steps for Pressure Grouting procedure of WTG Foundation

  1. Chipping of the pedestal
  2. Drilling in the raft region
  3. Vertical drilling in the pedestal region
  4. Rebar installation

(a) Chipping of the pedestal

(b) Drilling in the raft region

(c) Vertical drilling in the pedestal region

(d) Rebar installation

Case I

Project Overview :

• The foundation of the wind turbine was identified with cracks.
• Delay in the concreting of the slab and pedestal.

Conceptualisation of the Problem:

Cracks or cold joints were formed at the slab and pedestal region of the wind turbine foundation because the concrete was cast at different times. Analysis was carried out for the reduced properties of concrete by reducing the stiffness of the concrete.
Based on the results from the analysis the solutions were provided for the retrofitting.

Solution Provided by NeXHS:

To match with the stiffness criteria, introduction of studs along the circumference of the embedded can was proposed. Further, grouting was donein multiple places to increase the bonding between the existing concrete.

Reinforced concrete jacketing improves slab flexural & shear strength.

Case II

Project Overview :

The square foundation of the WTG tower was reported to have vibration which resulted in the loss of bond between the region of the embedded can and the underlying concrete area. NDT tests and bosrescopy were performed to evaluate the strength of the concrete.

Conceptualisation of the Problem:

Minor cracks were observed at the bottom portion, and it was inferred that the concrete at the bottom region of the foundation has lost contact with the embed can.

Due to the vibration, the concrete in the interface of the embedded can have reduced stiffness and strength.

The bottom layer of concrete modelled with a reduced elasticity modulus

Solution Provided by NeXHS:

To match with the stiffness criteria,introduction of studs along the circumference of the embedded can was proposed. Further, grouting was donein multiple places to increase the bonding between the existing concrete.

Removal of the existing Concrete

Introduction of threaded bars into the pedestal